Alpine Rotundo
Project Time: 24-38 hours
Project materials included:
4 layers Alpine Rotundo
91 pieces Alpine Rotundo single stones
48 pieces Alpine Large Rectangle stones
36 pieces Alpine Large Square stones
7 pieces Snap Edge restraint & 42 10” spikes
2 bags Sweeping Sand
Tools Needed:
String line, level, gloves, shovel, wheel barrow, tape measure screed rails & compacting plate.
Installation Instructions:
Step 1 - Prepare the site
Set stake in middle of desired area, attach a 8’ 8” string. Using marking paint, pull string tight and circle the parameter for dig out. Dig out 6” for gravel, sand & stones.
Step 2 - Compact base
Add 3”- 5” of 3/4 minus gravel into dug out area. Using a plate compactor run over the area 3 times. Okay to wet gravel for better compaction.
Step 3 - Screed the sand
Use 1” square tubing (or PVC pipe) and straight 8’ long 2”x 4”, pull sand across to make a smooth surface. When moving screed rails fill voids with sand and hand screed to make smooth.
Step 4 - Find the center
Remove the center stake, and hand float sand to fill in hole then lay 4 center pieces*. Continue: Circle row 1 uses 8 X-small*, Circle row 2 uses 16 small*, Circle row 3 uses 23 single stones*.
Step 5 - Lay circle rows
Continue: Circle row 4 will use 17 large recs*, Circle row 5 will use 21 single stones* & 21 large recs*, Circle row 6 will use 22 single stones* & 8 large recs* & 14 large squares*.
Step 6 - Finish
Circle row 7 will use 24 single stones* & 24 large squares*. Set edge restraint, compact stones, sweep sand into joints, compact stones again and sweep sand again to finish.
Uses
Architect Information
Are you an architect, and looking for more detailed product info? Check out our Architect's Resource page.
Locations
Western Interlock - Rickreall
10095 Rickreall Rd
Rickreall, OR 97371
503-623-9084
Western Interlock - Tumwater/Olympia
9145 Fassett St SW
Olympia, WA 98512
360-878-9301